225.27 Raceway Seal Conduits entering a building underground.

This requirement is to keep out moister, and water from entering a switch gear or panel board.  I have seen where services that where ran up the side of a pole from the utility have not been sealed and when it rained water came out of the meter can.  If I see it from the utility I try to get them to put duct seal or some other kind of sealant in the pipe.  The pipes don’t have to be run into a piece of switchgear or other equipment to be sealed off.

 

SEALS

SEALS A

Till next time work safe and be safe.

 

Jake